A sign is handled more often in transit than in its entire service life. It is lifted onto a truck, consolidated, stacked, lifted again at a port, dropped into a container, lashed, unlashed, hauled to a warehouse, then carried to a wall. Packaging is the only part of the project that nobody designs until the end, and it is the part that decides whether the installation day starts with a clean crate or a damage claim.

Packaging has to survive a sequence, not a moment
A crate is not tested by being dropped once. It is tested by a sequence: road leg to the forwarder, consolidation with other cargo, a sea leg of three to six weeks, port handling, a rail or road leg, then storage on site — often outdoors, often on a pallet in the rain.
Each stage loads the crate differently. Consolidation adds compression from cargo stacked on top. Sea freight adds humidity and condensation. Port handling adds impact at the corners. Site storage adds time and weather. The crate design should name which of those apply, because a domestic courier shipment and an LCL export are not the same problem.
Support the load path, not the face
The single most expensive packing mistake is letting the sign rest on its face. A cabinet or a set of letters should be supported through its returns, its frame or its back panel — the parts designed to carry load — with foam at the contact points and clearance under the face.
Four rules cover most cases: block the cabinet at its edges rather than its centre, keep the face at least 25 mm clear of any crate surface, never let a stud or a fixing bracket carry the weight, and pack letters so they cannot slide against each other. A letter that moves 10 mm in a crate will arrive with a polished edge that looks sanded.
Crate construction
Export crates for signage are usually plywood in the 12–15 mm range, built on skids of about 100 mm so a forklift can get under them without touching the sign. Internal battens keep the sides from bowing under stacking load, and the lid should be removable without a pry bar.
Three additions earn their place. A moisture barrier with desiccant protects a metal finish through a humid sea leg. A vapour-corrosion inhibitor sheet protects polished or plated surfaces. Tilt and shock indicators give the receiver evidence of what happened in transit — not proof, but a starting point that a carrier cannot easily dismiss.
Screws rather than staples for the lid, because a stapled crate is opened with a hammer and the hammer usually finds the sign.
Faces, fragile parts and the installation kit
Different components need different protection, and packing them together is usually wrong:
- Acrylic faces — flat, interleaved with foam or paper, never stacked directly against each other.
- Flexible faces — rolled around a core of at least 150 mm diameter, wrapped, and kept away from sharp hardware.
- SEG graphics — rolled in a tube; the frame ships separately as a kit.
- Backed neon — crated face-up, with the standoffs protected and the driver in its own carton.
- Drivers and power supplies — boxed separately, labelled to the branch they serve.
- Hardware and templates — bagged per letter, template rolled rather than folded.
The installation kit is part of the product. A crate that contains a beautiful sign and a bag of mixed screws has moved the problem to the site, where it becomes an hour of guessing and a trip to a hardware shop.
Match the crate to the route
Route decides dimensions before it decides anything else. A standard container has an internal height of roughly 2.39 m and a door opening slightly lower, so a crate that is 2.45 m tall will not go in upright regardless of what the drawing says. Air freight crates face their own limits on width and weight per piece, and LCL cargo is handled more often than FCL cargo, which argues for a heavier crate and more internal blocking.
Two route-specific notes: on LCL, assume something will be stacked on top, and design for it. On air, design for a forklift that may not exist at the destination — skids help, but so does a crate that can be lifted by two people at its ends.
The crate also has to survive being opened. A receiving site with no cutting tools will pry a lid with whatever is nearby; a crate designed with a marked opening point and a reusable lid survives the first inspection instead of losing its own protection in the process.
Moisture is the invisible damage
Most transit damage that is not visible on arrival is moisture. A container moving from a warm port to a cold one condenses water on the inside of the crate; a crate stored outdoors on site collects it from below. The result appears weeks later as a cloudy coating, a corroded edge or a driver that fails on first power-up.
Three layers handle it: a sealed moisture barrier around the unit, desiccant sized to the crate volume rather than a token sachet, and a vapour-corrosion inhibitor sheet against polished or plated surfaces. On a long sea leg, add a humidity indicator card inside the barrier so the receiver can see what the crate experienced.
A cabinet that is sealed for weather is not sealed for shipping. Internal condensation forms inside the sign as well as outside it, which is why the packing plan should say whether the unit ships with its face on or with vents taped.
Weight, palletising and stacking
Crate weight decides who can handle it. A unit over roughly 50 kg needs two people or a pallet truck; over 100 kg it needs mechanical handling at every transfer point, including the destination. State the gross weight on the crate and on the packing list, because the receiving site plans its labour from that number.
Keep the centre of gravity low and centred. A tall narrow crate is stable to build and unstable to move, and the failure usually happens at the first forklift. Where a crate must be stacked, state the stacking limit and design the lid and battens for it — otherwise the label is a request rather than a capacity.
Labels that make installation possible
Labels are the cheapest part of the shipment and the most useful on site. Every crate should carry the project reference and revision, the gross weight, the elevation reference it belongs to, orientation arrows, and a handling instruction such as “do not stack” or “keep dry” where it applies.
Inside, every letter should be labelled with the position ID from the drawing. On a set with repeated characters, the label is the only thing that tells an installer which “A” belongs to which opening — and a mislabelled letter is usually installed before anyone notices.
Evidence before the crate closes
Photograph the packing, not just the product: the load path and foam, the hardware bags, the labels on the closed crate, and the seal number. Record the gross weight and the packing list, and put the seal number on the shipping documents.
At receipt, photograph the crate before opening, then photograph the contents before unpacking fully. Note any damage on the delivery receipt at the moment of delivery rather than in an email the next day, because that notation is what a claim rests on. A signed clean receipt is very hard to reopen.
Event and multi-site transport
Event signage and multi-site programmes add a different constraint: the crate has to survive being used more than once. Reusable cases with foam inserts cut to the component shape, a packing diagram inside the lid, and a checklist taped to the case turn repacking from an improvisation into a routine.
For a rollout, keep the crate mapping consistent across sites. The same box number should hold the same elevation at every site, so a crew that has packed one site can pack the next without thinking.
Risk to control
| Transit risk | What actually prevents it |
|---|---|
| Face abrasion or cracking | Face kept clear of crate surfaces, interleaved panels, no load on the face |
| Compression from stacking | Internal battens, “do not stack” labels, crate rated for the load |
| Humidity and condensation | Moisture barrier, desiccant, VCI sheet on polished surfaces |
| Movement inside the crate | Foam blocking at edges, no loose hardware, per-letter bags |
| Wrong letter at the wall | Position ID labels inside, elevation reference outside |
| Disputed damage | Tilt/shock indicators, photographs, seal number, noted receipt |
Frequently asked questions
Does a wooden crate guarantee damage-free delivery?
No. It reduces risk. What protects the sign is the load path, the clearance around the face and the blocking that stops movement — the crate is only the box around those decisions.
Should the driver ship inside the sign?
Not for export. A driver inside a sealed cabinet is exposed to condensation and cannot be isolated during service. Box it separately and label the branch.
Can the template be folded?
No. A folded template introduces a crease exactly where the layout is most critical. Roll it in a tube.
Who pays for damage in transit?
That depends on the Incoterms and the insurance, which are commercial terms agreed before shipment. What matters technically is the evidence: photographs, indicators and a noted receipt.
Send the route, the crate limits and the elevation list, and the packing can be designed around the actual transit sequence. The wholesale signage programme notes cover repeat shipments, and the quality control checklist covers the inspection that has to happen before the crate closes.